AltaLink’s route still opposed

  • Dec. 15, 2010 4:00 p.m.

AltaLink has picked a preferred route for a new power line and one vocal opponent predicts the fight will be on to stop it.

The transmission provider has chosen to run the 500-kilovolt line next to an existing single 240-kilovolt power line west of Highway 2, roughly on a north-south line 10 kilometres west of Rimbey. The 330-to-365-kilometre line will connect the Genesee area southwest of Edmonton with Langdon, east of Calgary.

The western option will be listed as AltaLink’s first choice in an application expected to be filed with the Alberta Utilities Commission early next year. An alternate route that runs east of Red Deer will be presented as a second option.

The Alberta Utilities Commission is expected to hold a series of public hearings next summer before making a decision. If a decision is made before the end of the year, construction could start next winter. The line would be in operation in 2014.

Joe Anglin, leader of the Lavesta Area Group, a vocal critic of the plan to build the $1.1-billion line, as well as another $15.5 billion worth of proposed electricity upgrades, predicts AltaLink is in for a battle.

“This is an over-build beyond reason,” he said. The transmission plans on the books would be like building a 32-lane highway from Edmonton to Calgary.

Alberta’s massive electricity transmission expansion plans amount to public tax dollars being used to subsidize a handful of companies so they can reap big profits, he said.

Ultimately, the cost of the power lines will be passed on to power users, including households, and especially industry, the province’s biggest electricity buyers, in the form of dramatically higher bills.

Greg Troitsky, who farms just a few kilometres west of Rimbey, will avoid having transmission towers planted on his land this time around if the preferred route is chosen.

He counts himself among those who wouldn’t oppose a line if a convincing case were made that it is needed. That hasn’t happened.

“If they could actually prove there is a need for this line, people would feel a whole lot different about it,” Troitsky said.

Leigh Clarke, AltaLink’s senior vice-president of external engagement, knows there are some who will never be sold on the rationale for the line.

The line is needed, a fact that was determined during the last round of public hearings, said Clarke. The province has grown by a million people since the last major electrical infrastructure was built, and what is in place is on average nearly four decades old.

Clarke said the company learned some lessons from the last round of hearings and embarked on a lengthy public consultation effort with open houses in dozens of communities and meetings with thousands of landowners over the past year.

“I believe that has helped to engage the public and helped to reduce the concerns,” he said.

The route chosen is different than the previous proposal, which would have put a new line along side a pair of 240-kilovolt lines that run through Central Alberta just a few kilometres east of the single line chosen this time. The new line will parallel existing power lines for about 220 km.

Clarke said AltaLink looked at a broader area this time and decided the preferred route would have the least impact on property owners, the environment and agriculture operations. The preferred route passes within 150 metres of only 15 residences.

By Paul Cowley / Red Deer Advocate

Just Posted

PHOTOS: Ice racing at Mulhurst Bay at Pigeon Lake

Results of the ice racing event at Pigeon Lake

Maskwacis RCMP lay charges from home invasion

Four charged in alleged invasion using knives and gun on Samson Cree Nation - three injured

UPDATE: Highway 2 lanes were closed due to milk truck fire near Millet

A southbound truck hauling milk and cartons collided with a bridge

Ponoka Airport taxiway improvement costs overrun

The $328,000 project increased to $359,000, gravel cited as main reason for the increase

Ponoka County council looks at how it sees collaboration

County wants separate negotiations with Ponoka, Rimbey

WATCH: Ponoka residents enjoy first skate on ice path

A community initiative helped create a skate path for families in Ponoka.

Suspected Toronto serial killer targeting gay community arrested

A 66-year-old man is charged with first-degree murder in disappearance of two Toronto men

Barenaked Ladies, Steven Page, to be inducted into Canadian Music Hall of Fame

Canadian band to get top honours at 2018 JUNO Awards

B.C. out of the running for Amazon’s next headquarters

Toronto is the only Canadian city left in the running despite the province backing Metro Vancouver’s bid for new Amazon headquarters

Post interest rate hike debt tips

What to do about your debt and mortgages after the interest rate hike

Foreign workers sleeping in Alberta Burger King basement

Alberta Health Services said its inspectors found foreign workers sleeping in the basement of the Lethbridge restaurant

Court application halts release of bread price-fixing documents

Bread price-fixing documents won’t be unsealed Thursday, Loblaw says

Pharrell and N.E.R.D to headline NBA All-Star halftime show

11-time Grammy winner Pharrell and his hip hop-rock band N.E.R.D. will headline the halftime show at the 2018 NBA All-Star game in Los Angeles

Heritage Minister wants zero tolerance for harassment in entertainment industry

Heritage Minister Melanie Joly had two meetings to discuss harassment in the film, TV and theatre worlds

Most Read