Time to reconsider north-south power line

A year ago the Alberta Government appointed a Critical Transmission Review Committee to determine

Gerry Angevine, Guest Columnist

A year ago the Alberta Government appointed a Critical Transmission Review Committee to determine whether the Alberta Electric System Operator’s (AESO) proposal that two high voltage direct current (HVDC) north-south transmission lines be built because of occasional congestion on the Edmonton to Calgary corridor is reasonable.

In spite of the availability of lower-cost alternatives, the committee agreed with the AESO’s proposal, the Redford government accepted the committee’s recommendation, and AltaLink and ATCO Electric are now in the throes of planning to commence construction.

Unfortunately, the committee’s recommendation was not based on careful analysis. In fact, the recommended construction will result in overbuilding transmission lines at considerable and unnecessary expense to Alberta electricity consumers. For this reason, further work should be put on hold until a cost-effective solution is identified.

The process by which the committee sought to fulfill its mandate was inadequate and incomplete. Interested parties were granted only one hour to present their views to the committee, including discussion, compared with the great many hours that the commission presumably spent interacting with AESO officials. Following a compressed hearing process given the importance of its task, the committee simply summarized what it had “heard” before providing two pages of “analysis” that regurgitated the AESO’s main arguments and concluding that the AESO’s proposal was “reasonable.”

The committee failed to assess the benefits and costs to consumers pertaining to the recommendation that two north-south HVDC transmission lines are needed. With an estimated capital cost of $3 billion, building two north-south HVDC lines is by far the most expensive of available options. The AESO itself recently indicated that annual transmission system revenue requirements will jump from under $1 billion in 2011 to $2.7 billion by 2016 largely as a result this decision. Given the impact that this will have on electricity costs, one can only wonder whose interest the committee (and the government) is serving.

Based on AltaLink’s estimate that the annual cost of the two HVDC lines would be $344 million/year, every Albertan will pay an average of $75/year for these lines. While the committee suggests the cost on the average residential electricity bill will only be a few dollars per month, it misses the point that Albertans will ultimately also have to cover the higher costs faced by municipalities, hospitals, schools, restaurants, etc. Because of the cost, every effort should have been made to determine whether there are feasible alternatives to what the AESO recommended — such as building a single 500 kilovolt AC line or seeking solutions that avoid construction of major new transmission lines.

The committee accepted the AESO’s recommendation that DC lines be built in spite of costing an estimated $1 billion more than AC lines. Again, there was no attempt to justify the extra expense via cost-benefit analysis. Further, building two 500 kilovolt DC lines with a transfer capacity of 2,000 MW each would increase the Edmonton to Calgary transfer capacity from about 2,150 MW to approximately 4,000 MW. This is quite remarkable given that congestion has occurred very infrequently during the past six or seven years and that the committee heard the volume of north-south transfers is likely to decline in the future as aging coal-fired generators near Edmonton are retired and new gas-fired generation capacity such as the 800 MW Shepherd Energy Centre is built in the south.

The cost-benefit analysis provided in the University of Calgary School of Public Policy’s submission to the committee concluded that “the proposed construction of the two HVDC lines appears to be an over build of transmission capacity” which cannot be justified. Further, because of the location of new electric generation facilities, TransCanada suggested that “a review of the critical designation of some of the transmission lines should be conducted and perhaps deferral of one or both HVDC transmission lines may be warranted.

Because the AESO and the committee failed to demonstrate building two north-south HVDC transmission lines constitutes a cost-effective approach for addressing the transmission congestion challenges that the AESO claims need to be addressed, the Alberta government should immediately turn this important matter over to the Alberta Utilities Commission. The government has already acted on the committee’s recommendation that the Electric Statutes Amendment Act, 2009 be amended to give the commission responsibility for approving transmission lines that are proposed in the future. The commission should now also be asked to decide whether the benefits/costs of building the two HVDC north-south lines indicated as ‘critical” in the Electric Statutes Amendment Act, 2009 justify their construction when examined alongside possible alternatives. If not, it should be left to the commission to suggest solutions that best fit the needs of Albertans.

Gerry Angevine is a senior economist in the Fraser Institute’s Centre for Energy Policy Studies.

Just Posted

Pair arrested in Ponoka with several weapons, face 98 charges

Two men nabbed after early morning suspicious vehicle reported, stolen weapons found

UPDATE: 18-year-old Rimbey teen dies in collision

A portion of Highway 53 west of Rimbey is down to one lane while crews investigate

Ponoka County approves $70,000 to dredge Parkland Beach

Parkland Beach to see some dredging support from Ponoka County

Ponoka sets bylaw on cannabis retail, pushes for quick public consumption regulation

Town passes first reading on retail outlet bylaw, questions staff on need to separate public usage

Ponoka airport leaseholders to see second straight increase

Rates set to rise by 2.5 per cent when the calendar flips to 2019

U.S. congressman issues dire warning to Canada’s NAFTA team: time is running out

Canadian Foreign Affairs Minister Chrystia Freeland is expected to resume talks with the U.S.

Mistaken identity: Missing dog claimed in Moose Jaw belongs to another family

Brennen Duncan was reunited with a white Kuvasz that was found in Saskatchewan

Potential replacements for Phoenix pay system to start testing soon: Brison

Testing of prototypes to replace troubled federal pay system will begin within weeks

Nanaimo’s Tilray Inc. briefly the world’s largest cannabis company

The company, only listed in the US, nearly reached $300 in afternoon trading on Wednesday

Woman who helped kidnap Elizabeth Smart released from prison

Smart was 14 years old when she was snatched from her Salt Lake City home in 2002 by street preacher Brian David Mitchell

New York books editor out after backlash over Jian Ghomeshi essay

Ian Buruma, who was appointed as editor of the New York Review of Books in late 2017, no longer works for the publication

Competition tribunal to hear B.C.-based case on airline food starting in October

The competition commissioner argued Vancouver airport authority had exploited its market position

Seek compromise with U.S. on cannabis at border, lawyers urge Ottawa

U.S. Customs and Border Protection agency sent tremors through Canada’s burgeoning cannabis sector

Most Read